1. Pre-Commissioning

In order to minimize the on-site commissioning time and help eliminate the adverse effects of reduced commissioning timescales, as  much pre-commissioning process as possible should  be performed off-site. 

Off-site pre-commissioning tasks include: 

  • Control Application software. Check DDC routines with realistic default values. A witness some or all of these checks at this time is possible. 
  • A record of all settings, set points and offsets. Check specified set points have been configured. Interlocks and Control loops 
  • Sequence of operations as specified. 
  • Start-up and shutdown procedures.
  • Plant changeover.
  • Alarm functions.
  • User interface software.
  • Control panels, Factory aceptance tested.
  • Integration gateways (partial).

off site